SOLHAR Botswana – Stage Tank for Water Storage and to Pump Water

Botswana Stage Tank – Water Storage and Pump Project

Grade B container purchase and delivered. Not in too bad of a shape.
Details about this Project;
THE CLIENT’S REQUEST:
Our client in Botswana requested us to come up with a solution for a stage tank to be able to store and pump water out of the pit area. Because of the depth of the pit, it is not feasible to pump water all the way up and out. The pumps required to do this is not cost effective. To be able to use smaller pumps the water needs to be pump in stages i.e. halfway up and then the last bit out of the pit area.
THE SOLUTION:
To achieve this, you need to be able to store large quantities of water before pumping it further.
We did some investigation and realized that is you reinforce and seal a container it will work perfectly.

Our Solhar team started by strengthening the container frame from the outside.

Container is boxed up and twice as rigid as before.

The original floor in containers are made from wood which needed to be removed and new floor installed made from sheet metal.

To assist with the pressure of weight of 80000lt, we installed pipe supports on the inside of the container.

Access hatches were also fabricated for easy access for maintenance and repairs if needed.

Part of the request was to be able easily place the stage tank in new positions as required.

The easiest way to do this, was to build a sled on which it can be pulled.

Due to the size of the sled, it was assembled and welled in 2 halves.

Once welded they were joined together and,

The container was placed on top of the sled and welded in position.

A water test showed some leaks, which was quickly repaired.
Considering it was a grade B container there was very little water lost.


We applied a water resistance primer to the inside on the tank.

Nice inside paint job!

Same water-resistant primer was applied on the outside.

Final paint applied to make the staged tank look brand new.

Loaded and on its way to its destination in Botswana. The tank worked so well that they ordered another on 3 months later.

Collection of projects done by the SOLHAR Team
SOLHAR Energy Solutions and Engineering in Kimberley and Botswana
View some of our other projects completed by SOLHAR;
- All
- BAOBAB SAFETY TREE
- Botswana Stage Tank
- BULL RUN 2024
- CNC Plasma Cutting
- Dozer Blade - Idwala Lime Mine
- ESKOM BUILDING
- GHAAP
- High Wear Plate Liners
- JOINTSHAFT
- KIMBERLEY WATER SHUTDOWNS
- PCCU PROJECT
- Plate Work
- PROJECTS
- Ready-Mix Concrete Cement Projects
- Refurbishment
- Riverton Clarifier Refurbishment
- SOLHAR Botswana
- SOLHAR Civil Projects
- SOLHAR Performance Evaluation
- Stainless Steel
- Stockpile Crusher
- Structural Steel
- Wi-Fi Towers
- Wingwalls

Solhar Energy Solutions & Engineering Botswana Contact:
ROY DE BRUIN
+26771660127
roy.debruin@solhar.co.za
Solhar Energy Solutions & Engineering Contacts:
GERRARD BOOYENS
082 551 4082
gerrard.booyens@solhar.co.za
KEVIN HARDING - Ready-Mix
083 256 9975
kevin.harding@solhar.co.za
BRIAN DANIELS
082 481 0616
brian.daniels@solhar.co.za
JOHAN LE ROUX - Civil Engineering
072 672 7427
johan.leroux@solhar.co.za
CONTACT US;
Our Kimberley Branch is situated at 8 Hendrik van der Bijl, Kimdustria, Kimberley, 8301, Northern Cape, South Africa

Brave men are not born! They are molded. SOLHAR constantly thrive to achieve the set goals monthly and we maintain our identity in what we stand for. If we do not stand for something we might fall for anything. May GOD always stay our protector in whatever project we complete, big or small. To HIM alone the glory and honor - Hallelujah

Men tend to lose their identity in these trying times. We are identified as hard working men taking ownership and responsibility as good, loyal GOD fearing men for our households! BE THE MAN everyone talks about. Stand out in the crowd. Believe and NEVER forget your role and responsibility.

Deliver service. Something we tend to be dislodged from in society in having a basic right to services rendered around us. If GOD stops to deliver the sun, moon, and stars on time we are done with and therefore we strive to keep our focus on delivery of service to our customers.